At the end of 2015, Six Construct was awarded the contract to design and build the marine structures, which consist of a double berth jetty for FSU and LNG carriers, protected by a 500-m-long and 15-m-deep breakwater. The design phase was carried out by BESIX Engineering. The Final Notice To Proceed, received mid-November 2016, started the deployment of our site team mobilized to overcome the challenges of this offshore project.